Water Line Upgrade Project
Alligator Point Water Resoucres District is an Independent Special District with it's own governing body. Questions for this project should only be directed to District staff or Engineers. Franklin County will not be able to provide information on this project.
Updates from 850 Construction, our contractor for the project, will be provided weekly. Should you have additional questions, please reach out to the Office Manager or Maintenance Supervisor.
850-349-2274, Office
850-566-0821, Mr. Robin Arnett Maintenance Supervisor
850-509-0221, Mrs. Sara Turner, Office Manager
pointwater@fairpoint.net
www.alligatorpointwater.com
UPDATE FOR 6/12/25
Update on Alligator Point Water Distribution Expansion
I hope this message finds you well. I wanted to provide an update on the ongoing water distribution expansion project at Alligator Point.
We received a couple of complaints from residents regarding road damage, road construction signs, and busted concrete from the digging. I am pleased to inform you that these matters have been addressed and resolved.
Additionally, I have reached out to the Virginia-Franklin County Road Department, inquiring if there is an empty lot owned by the county nearby. We hope to obtain approval to use this lot for dropping off concrete and debris to keep the job site clean. We will haul off the debris after the project is completed. We are currently awaiting a response on this matter.
As we worked our way around Pine Street, we noticed a leaning power pole at the intersection of Pine and Oak Street. A report has been filed with FPL, reference number 100017400638.
The pipe & hydrants along Pine Street have been completed, and the bore at Pine & Alligator.
A small portion of Maple has been started. We will be completing it and then over to Magnolia to conclude the Sun N Sand Subdivision.
Southern Dunes Subdivision will follow.
Please feel free to reach out if you have any questions or need further information.
Best regards,
Kelly Roberts
Project Manager
kellyr@850-construction.com
(850) 441-3172 Ext 6
UPDATE FOR 6/4/25
Alligator Point Water Distribution System Expansion
Project Update: Pipe Installation Progress and Permit Submission
I hope this email finds you well. I wanted to provide an update on our ongoing project.
Despite facing a few challenges, we have successfully laid approximately 2,000 feet of pipe. There should be significant progress moving forward.
During this process, we were contacted by Howard from the Franklin County Road Department, who inquired about not being notified of our project. Following this, I was introduced to Virginia within his office.
On June 1st, I submitted the requested application for the permit, along with the necessary plans and notice to proceed.
UPDATE FOR 5/23/25
Alligator Point Water Distribution System Expansion
Project Update:
- 5/21 Discovered the locates for Duke are outsourced to USIC. Spoke with Myron-USIC, he was on site doing the locates that afternoon.
- 5/22 Material delivery. Dropped at Bald Point & Dunes.
- 5/22 300 Played out 300 feet along Pine Street with flags & paint.
- Due to the late response of the locates from USIC/Duke and the holiday weekend. We decided it's best to start work on next Tuesday 5/27.
- Robin mentioned he noticed a homeowner had their driveway marked for improvement but would reach out to inform them of the work that would possibly interfere.